|
Lax Oversight Leads to Lost Revenue and
Safety Concerns
View Audit
View
Parks Department's Recent Letter
The City’s Parks Department does a poor job of ensuring that
concessionaires comply with the capital improvement provisions of
their agreements, according to an audit issued today by New York
City Comptroller William C. Thompson, Jr.
Auditors found that capital improvements totaling nearly $10 million
were not completed at 37 of 58 concession s sites visited, that
had improvements at five sites been completed, the City could have
garnered nearly $300,000 in extra concessionaire fees, and that
a lack of documentation between concessionaires and the Parks Department
made it difficult to determine the status of work on projects.
“The Parks Department must do better in overseeing concessionaires,”
Thompson said. “These facilities are spread out across the
City and serve millions of New Yorkers every year. It is of significant
concern that the Parks Department is not properly supervising them
to ensure that the required improvements are made.”
The Parks Department monitors various City concessions, including
ice rinks, marinas, golf courses and restaurants. Under their agreements,
many concessionaires are required to make and pay for capital improvements
to the facilities they operate. The Parks Department’s Revenue
Division is responsible for overseeing concessionaires to ensure
that required capital improvements are completed.
The scope of the Comptroller’s audit covered concession agreements
in effect during Fiscal Year 2003 that required capital improvements.
Auditors also discovered poor conditions at certain concessions,
potentially posing a risk to the public. These conditions included
missing and cracked exterior facade panels at Terrace on the Park
in Queens, an inaccessible restroom at the Prospect Park Tennis
Center in Brooklyn, rotting piles and an unstable bulkhead at the
Dyckman Street Marina in Manhattan, and missing fire protection
at the Clove Lakes Cafe in Staten Island.
“Safety should be the Parks Department’s major concern,”
Thompson said. “The Department must immediately, if it has
not already done so, issue written notice requiring that the concessionaires
correct the conditions noted in my audit.”
The audit concluded that the Department does not have an adequate
project management system in place to ensure that concessionaires
complete capital improvement projects. Auditors noted that Parks
did not track the progress of capital improvements against start
and completion dates prescribed in agreements, and it did not conduct
routine inspections of capital improvement work performed. Auditors
also noted that the Department did not review invoices, canceled
checks, and other related documentation submitted by concessionaires
and it did not update tracking documents to reflect changes in capital
improvement requirements.
These deficiencies led to capital improvements not being completed.
The 37 instances in which capital improvements were not completed
were located in all five boroughs and included Wollman Rink in Central
Park, Shea Stadium in Queens, Pelham Bay/Split Rock golf courses
in the Bronx, and the South Shore Golf Course on Staten Island.
“The Parks Department needs to implement a project management
system as quickly as possible,” Thompson said. “At a
time when the City is still struggling with huge budget deficits,
we cannot afford to forgo millions of dollars in required improvements.”
The audit also revealed that the Department did not assess liquidated
damages against concessionaires who failed to make the required
improvements by a specific date, as allowed for by the concession
agreements. Department files did not indicate why six concessionaires
were not assessed liquidated damages, which would have amounted
to nearly $1.5 million.
The audit noted that a lack of documentation between concessionaires
and Parks was a major problem. Ten of the 37 concessionaires who
had not completed their capital improvements claimed that the Department
had authorized them to modify or cancel the required capital improvements.
However, neither side could provide the auditors with documents
showing that changes were requested by the concessionaires and approved
by the Department in any of the cases.
Auditors additionally found that the Department did not follow
its procedures for certifying the completion of projects. While
the auditors identified 18 concessionaires who completed their capital
improvement requirements, the Department only certified one as complete.
The audit made nine recommendations to the Department, including:
- The Department should establish a project management system
to monitor the progress of concessionaires in completing required
capital improvements.
- The Department should issue notices-to-cure to concessionaires
who have not completed the capital improvements required by their
agreements.
- The City receives compensation equivalent to the value of the
capital improvements it is forgoing before it approves any modifications.
- The Department should ensure that modifications to capital improvements
are documented with formal agreements between the Department and
the concessionaires.
- The Department should assess liquidated damages when concessionaires
fail to complete capital improvements in accordance with their
agreements.
- The Department should issue certificates-of-completion to those
concessionaires who have completed their capital improvements.
###
|